Towers

 
NCRT
 
Concreting
 
 

Concreting

Concreting

07:45 16m3 arriving


     
 

Pumping

Starting within the inner of the NCRT base, pumping concrete

     
 

Filling

Using a so called ''vibrator for concrete". A thin neelde with motor which prevents air bubbles within the finished concrete. (white helmet = PA1A)

     
  Filling 2/3

from the inside to the outside...
     
 

Formwork

Concrete is compressing the scructure...

     
 

Finish

The gap is filled with 16m3 concrete (floor = 4m3) which makes a total of 20m3 from the NCRT.

     
 

Cleaning

Inserting a sponge into the hose (clean the hose)

     
 

Finish

Looking inside the NCRT...

     
 

Barns

Using this tool to smoothen the surface of the concrete.

     
 

PA1A Handwork

After 5 hours (and a clean-up shower) concrete barns smoothing the surface

 

* drying the work clothes @ guy wires

     
 