Tower preperations
 
 

Drilling

The Towerbase

Water drainage 32mm hole drilling


     
 

PVC

Before concreting.

     
 

Drain

When the towerbase is filled with concrete it needs a drain otherwise the innerring will be flood with water.

     
  Cutting

Inside the towerbase cut superfluous construction steel
     
 

Overview

Towerbase

     
 

Casing

Drilling 3x 100mm casing to feed the coaxial wires and power supply.

     
 

Countermould

Towerbase with wooden bars.

     
 

Position

Of the countermould onto the towerbase

     
 

Pipe sleeve

4x 110mm / 3.2mm thick

     
 

Position

Throught the mold

     
 

Rebars

Finishing the formwork by adding extra rebars and top layer rebars.

     
 

Spacer

Cutting four holes with 30mm distance, and saw the wooden spacer in half.

     
 

Position

Keep them together when poring concrete

     
 

Detail

Pipe sleeves underneath tower base construction. (closer look @ the gear)

     
 

Formwork

Formwork in detail. Clamps to position the site baulk.

     
 

PVC

Spacers and drain.

     
 

Anchoring

Achoring the concrete formwork with standard tools...

     
 

Beaming...

Take a look at the surrounding, great HF take-off....

     